Construction Update January 2026

22 January 2026

Construction at Park Lake Stages 6 and 7 continue to progress well, with key works advancing across the site. Here’s the latest on what’s happening this month.

This Month’s Progress

Earthworks: Cut to fill works are ongoing, shaping the land for upcoming stages.

Water Reticulation: Internal water reticulation works are continuing.

Telstra Realignment: Preparatory works for remobilisation have been completed.

Electrical Installation: Ongoing works are ensuring the estate is ready for future connections.

Roadworks: Road widening along Redbank Creek Road and construction on Dartnell Place are progressing.

Upcoming / Ongoing Works

Earthworks: Final trimming and continued cut to fill works will resume.

Water Reticulation: Internal reticulation almost complete, with external works set to commence.

Telstra Works: Installation will begin once the team remobilises.

Electrical Works: External electrical installation will continue.

Roadworks: Widening on Redbank Creek Road, Dartnell Place, and the commencement of Hamilton Drive will continue.

Join the Park Lake Community!

This is a rare opportunity to secure your place in this peaceful, natural setting. You’re not simply building a house. You’re choosing a lifestyle measured by what surrounds you: the view from your deck at sunrise, the way the wind moves through the gum trees, and the quiet confidence that comes from securing land of this calibre. Don’t miss out and secure your block today!